Baltimore, MD

Application

Water Storage

Construction Date

2020

Capacity

(3) 22,000,000 gallons (300'-0" ID x 41'-0" SWD)

Owner

Baltimore County, MD

Consulting Engineering

Gannett Fleming

In 2020, Preload successfully completed the largest prestressed concrete tank reservoir project in the history of the industry. As the General Contractor of this $75,000,000+ project, Preload was responsible for all aspect of project execution including: excavation of over 1,000,000 yd3 of soil, installation of large diameter, interconnections, vault structures, sodium-hypochlorite disinfection facility, electrical, instrumentation & various other project aspects. The three AWWA D110, Type 3 prestressed concrete reservoirs were each 22,000,000 gallons with column supported, flat-slab roofs and double concentric ‘C’ precast concrete baffle walls. The structural tank floor was designed to support the interior concrete baffle walls & roof columns.

Preload’s Area Manager, Bob Barbarisi and Project Engineer, Sean Vorsteg coordinated multiple subcontractors while managing a demanding schedule and maintaining environmental compliance. Brett Henning, PE worked with the project engineer, Gannett Fleming, to develop a final tank design which met owner’s goals for design, function, aesthetics and long-term durability. Daniel Almanza directed the largest on-site crew of craftsmen in Preload history to construct the tanks efficiently and within the project schedule.

2020 CONCRETE DECISION AWARD, TOP TANK OF THE YEAR - Runner-up